First Term Is For Project Initiation – Osita Chidoka
As shared by Osita Chidoka…
It takes about 1 to 2 years to bring an infrastructure project to FEC.
Initial Project design 6-12 mths
Procurement of consultant 6 mths
Full design and costing 6-9 mths
Procurement of contractor 3-6 mthsAny awarded project is 30% done. 1st term is for project initiation
Share your thoughts